perimeter drain being laid out
nice form, joel. glenn, get to work.

Bob, pumped to be building ICF foundation
Well, a series of events has occured since the last post: perimeter drain installed, ICF (insulated concrete forms) were installed as the foundation walls, and then the walls were filled with concrete. The biggest deal was the concrete loaded into the ICFs...Joel was so nervous that the forms might bust - a very possible happening - but it was a success! Then, once that was done, Bob the Builder laid down the floor joists in. And, voila - looks like a basement!
Back fill was done Thursday, June 3 and now we can walk around the back yard without fear of falling into a big hole.
Still, I'd like to see more progress... I want it to start looking pretty ;)